NEW BUILD UPDATE – November 2022

NEW BUILD UPDATE – November 2022

Since project commencement, OHMG have completed their site welfare area, temporary boundary  fencing and established a site access from Prince Andrew Way.  Soil stabilisation works are underway to all aspects of the site, excavation works to the building  footprint area are to commence over the coming weeks which will enable the formation of concrete retaining walls as part of the split level school construction. 

  • Formation of Temporary Site Access Road from Prince Andrew Way
  • Reduced Level Dig progressing to North of site- Proposed grass pitch area
  • ATG soil stabilisation progress to the West- Proposed Rugby Pitch
  • CFA Piling commenced to retaining wall
  • Soil Stabilisation in progress to the East Section of the site (Proposed Service Road area)